Khuzawayo Construction a local sub-contractor expects to use 19 675
pockets of cement for 2021. Carrying costs are R 6.25 per unit and
order costs are R 43.55. The organization works 315 Days per year.
Determine:
3.1.1 The Economic Order Quantity (EOQ)