Consider a job which requires four activities – cutting,assembly,finishing and packaging.four workers are employed to perform these activities. The time required by them to perform these activities are as. Activities Worker-1 Worker-2 Worker-3 Worker-4 C 14 12 15 15 F 21 18 18 22 A 14 17 12 14 P 6 5 3 6 How should these activities to be assigned to the workers, so that the job is completed in minimum time?
Consider a job which requires four activities –
cutting,assembly,finishing
and packaging.four workers are employed to perform these activities.
The
time required by them to perform these activities are as.
Activities Worker-1 Worker-2 Worker-3 Worker-4
C 14 12 15 15
F 21 18 18 22
A 14 17 12 14
P 6 5 3 6
How should these activities to be assigned to the workers, so that the
job is completed in minimum time?


