Activity “L”, which had a normal time of 9 weeks and a crashed time…
Question Answered step-by-step Activity “L”, which had a normal time of 9 weeks and a crashed time… Activity “L”, which had a normal time of 9 weeks and a crashed time of 6 weeks, actually took 11 weeks to complete. What will happen to the project schedule given that activity has been delayed? Business Management Project Management OPMA 317 Share QuestionEmailCopy link Comments (0)