A project is made of the following activities: Complete the table…

Question Answered step-by-step A project is made of the following activities: Complete the table… A project is made of the following activities:  Image transcription textTask Duration Predecessor(s) ES EF LSLF slack A 2 B 20 A C 5 A D 20 C E 17B.C,D F 11 D G 2 E.F… Show moreComplete the table above – ES, EF, LS, LF, Slack (15 points)What is the critical path? What is the project duration? (5 points)Refer to the critical path you found in 2. Assume that every activity is normally distributed. Each activity’s mean is given in the table above. Each activity’s standard deviation is 20% of its mean (for example, the mean duration of activity A is 2 and its standard deviation is 0.4). What is the probability that the project will last more than 48 days? (10 points)Note: Please provide complete solution with the full explanation including all the formulas in Excel. Business Management Project Management MGMT 3530 Share QuestionEmailCopy link Comments (0)