A PERT project is detailed in the table below. Durations are given…
Question Answered step-by-step A PERT project is detailed in the table below. Durations are given… A PERT project is detailed in the table below. Durations are given in days.ActivityPredecessorsOptimistic durationPessimistic durationMost likely durationExpectationVarianceA-232927 BA465854 CA222826 DA304238 EB232927 FB, C212725 GC, F456357 HG232927 IF, H283432 JE, I333937 KF, H, I243028 Draw an activity-on-node network representing this project.Give the expected duration and variance of each activity in the table. What is the expected duration of the project?What is the variance in the project’s duration?How many days are needed for the project to be 80% likely to be completed? Engineering & Technology Industrial Engineering Operations Management BBA ICMB Share QuestionEmailCopy link Comments (0)