A PERT project is detailed in the table below. Durations are given…

Question Answered step-by-step A PERT project is detailed in the table below. Durations are given… A PERT project is detailed in the table below. Durations are given in days.ActivityPredecessorsOptimistic durationPessimistic durationMost likely durationExpectationVarianceA-232927  BA465854  CA222826  DA304238  EB232927  FB, C212725  GC, F456357  HG232927  IF, H283432  JE, I333937  KF, H, I243028  Draw an activity-on-node network representing this project.Give the expected duration and variance of each activity in the table. What is the expected duration of the project?What is the variance in the project’s duration?How many days are needed for the project to be 80% likely to be completed? Engineering & Technology Industrial Engineering Operations Management BBA ICMB Share QuestionEmailCopy link Comments (0)