A contractor needs to stockpile 650 CY of gravel at a site. The…

Question Answered step-by-step A contractor needs to stockpile 650 CY of gravel at a site. The… A contractor needs to stockpile 650 CY of gravel at a site.  The gravel has an angle of repose of 35°.If the gravel is stored in conical piles 8 ft tall, how wide is the base of each conical pile and how many conical piles are required?If the gravel is stored in a triangular bank that is 15 ft wide at the base, how tall and long is the spoil bank.Looking for some assistance as I am unsure how to properly complete without having a Load Factor as well. normally it would be the Bank Volume/Load Factor?  Business Management Project Management CECM 670 Share QuestionEmailCopy link Comments (0)