Consider a job which requires four activities – cutting,assembly,finishing and packaging.four workers are employed to perform these activities. The time required by them to perform these activities are as. Activities Worker-1 Worker-2 Worker-3 Worker-4 C 14 12 15 15 F 21 18 18 22 A 14 17 12 14 P 6 5 3 6 How should these activities to be assigned to the workers, so that the job is completed in minimum time?

Consider a job which requires four activities –
cutting,assembly,finishing

and packaging.four workers are employed to perform these activities.
The

time required by them to perform these activities are as.

Activities Worker-1 Worker-2 Worker-3 Worker-4

C 14 12 15 15

F 21 18 18 22

A 14 17 12 14

P 6 5 3 6

How should these activities to be assigned to the workers, so that the
job is completed in minimum time?