https://www.onlinefreelancersnetwork.com/wp-content/uploads/2020/08/logoOFN.png00online_qhttps://www.onlinefreelancersnetwork.com/wp-content/uploads/2020/08/logoOFN.pngonline_q2023-01-10 23:20:372023-01-10 23:20:378. XYZ firm is preparing their monthly productivity report. Their monthly costs are shown below. Calculate the a) labor productivity b) machine productivity c) the multifactor productivity of dollars spent on labor, materials, and energy. Average labor rate is $18.00. Units produced: 1800 Labor hours: 1975 Machine hours: 425 Materials cost: $81000 Energy cost: $21600